AP Govt's 1000 MW Solar Project To Ensure 9 Hours Uninterrupted Power To Farmers While Reducing Losses

 - Sakshi Post

The Andhra Pradesh Government’s tender for the development of6,400 MW solar power plant with an aim of reducing the subsidy burden resulting from the supply of uninterrupted free power to farmers across the state has made headlines in the recent past. The process has resulted in Government securing close to 14,000 million units of power per annum at a tariff of 2.48 per kWh, which is the significantly lower than the tariff at which AP Distribution Utilities are procuring power.  Supply of free power to farmers is of paramount importance. However, this entails a huge subsidy burden on the state government. The state is having to incur close to Rs. 10,000 crores as a subsidy to meet the revenue gap of Distribution utilities.

The key ingredient of the subsidy component is the power purchase cost which as on date is prohibitively high. Another element contributing to the huge power purchase cost is the burden of the PPAs executed by the previous TDP Government at exorbitant tariffs. The average power procurement cost of the State as of now, is close to Rs. 5.2 per kWh. Therefore, the present Government has formulated the approach to procure power from a 6,400 MW solar power projects to be set up in the State. This would ensure reliable daytime power to the farmers and also reduce the subsidy burden on the government due, thereby making the functioning of the sector, sustainable. This low tariff of Rs. 2.48 would result in a savings of nearly Rs. 3,800 crores in the very first year and this savings is likely to increase over the years, considering the fact the present tariff of 2.48 for the energy from the 6,400 MW solar power project would remain constant over the next 30 years, whereas the cost associated with power from some of the other sources is likely to go up. The present value of benefit accruing to the Andhra Pradesh Government exchequer over the life of this project can conservatively be estimated at Rs. 50,000 crores.  Further, the plant was conceived on BOT basis and would therefore be transferred to the State after the expiry of the PPA. At the time of transfer, the plant would be operating at 18% CUFensuring plentiful supply of power at very low cost.

It is important to note that the authorities have adhered to all the guidelines prescribed by the Ministry of New and Renewable energy in an attempt to make the process as transparent and objective as possible, unlike never before. Apart from giving the potential bidders a month’s time from the date of issuance of the notification, the concerned authorities have also run the bid document through the judicial preview process to ensure that the process undertaken is implemented in a fair and transparent manner.Thre transparent manner of processing the bids along with the reverse tendering mechanism has ensured the discovery of the low tariff. The tariffs discovered are as follows,

S. No.

Location/ Solar Park Name

L1 Bidder(s)

Bid Capacity (MW)

Capacity Won (MW)

Final Tariff (INR/kWh)

01

Chakrayapet Ultra Mega Solar Park, Chakrayapet Mandal, YSR Kadapa District

NTPC Limited

600

600

2.48

02

Thondur Ultra Mega Solar Park, Thondur Mandal, YSR Kadapa District

Shirdi Sai Electricals Limited

400

400

2.49

03

M.Kambaladinne Ultra Mega Solar Park, Mylavaram Mandal, YSR Kadapa District

Adani Renewable Energy Holding Twelve Limited

600

600

2.49

04

Pendlimarri Ultra Mega Solar Park, Pendlimarri Mandal, YSR Kadapa District,

Adani Renewable Energy Holding Twelve Limited

600

600

2.49

05

Rudrasamudram Ultra Mega Solar Park, Donakonda Mandal, Prakasam District

Adani Renewable Energy Holding Twelve Limited

600

600

2.49

06

CS Puram Ultra Mega Solar Park, CS Puram Mandal, Prakasam District

Adani Renewable Energy Holding Twelve Limited

600

600

2.58

07

Uruchintala Ultra Mega Solar Park, Tadipatri Mandal, Anantapuram District

Shirdi Sai Electricals Limited

600

600

2.48

08

Kambadur Ultra Mega Solar Park, Kambadur Mandal, Anantapuram District

Torrent Power Limited

300

300

2.47

Shirdi Sai Electricals Limited

600

600

2.48

HES Infra Private Limited

600

300

2.49

09

Mudigubba Ultra Mega Solar Park, Mudigubba Mandal, Anantapuram District

Adani Renewable Energy Holding Twelve Limited

600

600

2.49

10

Kolimigundla Ultra Mega Solar Park, Kolimigundla Mandal, Kurnool District

Shirdi Sai Electricals Limited

600

600

2.48

The bid received for development of project in CS Puram is higher at Rs. 2.58 per kWh and the committee is examining whether such a high-priced bid should be accepted.

Tenders have been filed by big players such as NTPC Adani group and Torrent power placing bids to develop the project. The first phase which stretches over 10 different

locations has attracted a total of 24 bids in all. It is heartening to note that, owing to the present Government’s approach to evolving a robust commercial structure for the project that contributes to the sustainability to the State Energy sector and simultaneously safeguards the interests of all the stakeholders, has resulted in such an overwhelming response for the tender.

At this juncture, it would not be out place to recall the damage done to the energy sector during the TDP regime. During the period 2014-19, the debt in the sector has risen from Rs. 33,500 crores to Rs. 70,250 crores, total payables of the sector have risen from Rs. 2,893 crores to Rs. 21,500 crores during the five year period. As on 31st March, 2019, the negative net worth of both the distribution utilities was to the tune of Rs. 19,920 crores. DISCOMs with exhausted borrowing limits; increased annual revenue gap during the five year TDP tenure owing to high-cost renewable energy purchases; and unavoidable payment of fixed-costs to thermal power generators to accommodate the high cost renewable power, were few challenges the sector was facing when the present Government came to power. The TDP Government has executed PPAs to procure large capacity of wind power at an exorbitant tariff of Rs. 4.84 per kWh along with income tax and electricity duty reimbursements. The TDP Government has also executed PPAs to procure large quantities of solar power at Rs. 5.25 per kWh to Rs. 5.90 per kWh during the period 2014-2017. The developers got unreasonably high returns on their investments and the State Government and the DISCOMS have been subjected to a very huge financial burden owing to these high priced PPAs. It is important to note that in 2017 alone, 41 wind PPAs were executed by the TDP Government at the expensive tariff of Rs. 4.84 per unit, as described above. As against that, a tariff of 2.43 per kWh was discovered in the GUVNL (Gujarat Urja Vikas Nigam Limited) wind power tender. Further, all the wind power PPAs executed by the TDP Government were on nomination basis and not on competitive bidding basis.

It is important to note that previously, when the prevailing cost of thermal power was aroundRs. 4 per kWh, the TDP Government executed contracts with companies, to procure power at tariffs going way beyond Rs. 5 per kWh. Therefore, the distribution utilities were forced to replace low cost power with high cost power. Unlike the previous government, the present dispensation is committed to executing agreements for procuring power at tariffs significantly lower than the current prevailing thermal cost of around Rs. 5 per kWh, thereby safeguarding state resources in the process.

whatsapp channel


Read More:

Advertisement
Back to Top